Reston's transportation advisory board holds its next meeting Dec. 10 as the panel advances work on intersection improvements and grapples with rising infrastructure costs.
The Reston Transportation Service District Advisory Board (RTSDAB) meeting is scheduled for 6 to 8 p.m. at the North County Governmental Center Community Room, 1801 Cameron Glen Drive, according to the county's transportation page.
The board, chaired by Adam Rubinstein, advises the Fairfax County Board of Supervisors on the annual tax rate for the Reston Transportation Service District, project priorities and the Reston Road Fund.
Three intersection projects moving forward
At its March 10 meeting, the board unanimously approved a motion by Rubinstein, seconded by member Robert Goudie. The motion authorized conceptual design for the district's top three intersection projects at up to $1 million each, according to meeting minutes.
Those three intersections are Reston Parkway at Bluemont Way, Reston Parkway at New Dominion Parkway, and Hunter Mill Road at Sunset Hills Road, according to a fall 2026 board presentation. Draft scopes for the projects were emailed to board members on Oct. 13, with a Nov. 13 deadline for comments to staff.
The board retained all eight original intersection projects in its plan at the March meeting. Hunter Mill District Supervisor Walter Alcorn attended that session, along with staff from the Fairfax County Department of Transportation (FCDOT).
The board's Oct. 21 agenda also listed a bylaws update and rate recommendation as action items, plus a service district financial update.
Costs climbing, revenue still early
The service district's total revenue obligation stands at $178.6 million in 2025 dollars. As of Oct. 1, 13% of that amount had been collected, according to the fall presentation.
The district had spent $685,000 in total through fiscal year 2026 on two projects: Baron Cameron Avenue at Reston Parkway and Fairfax County Parkway at Sunrise Valley Drive.
Intersection improvements carry an estimated cost of about $99 million, according to the March meeting minutes. The planned grid of streets is estimated at about $169 million. Staff noted a projected shortfall of about $94 million.
A March 2026 presentation to the board showed the revised 2025 cost estimate for the district's funding plan contribution had risen to $226 million. That is roughly a 60% increase over the 2017 estimate of about $140 million, driven by construction cost inflation measured by the National Highway Construction Cost Index.
The grid of streets carries a total estimated cost of $1.021 billion, with $94 million from the service district and the rest from the Reston Road Fund and in-kind contributions, according to the March presentation.
Board also weighing bylaws changes
The March minutes noted challenges filling board seats. Staff member Shyamali Hauth from the Hunter Mill District office was to prepare recommendations for a possible bylaws update to reduce the number of required positions. No current members would be removed under such a change, according to the minutes.
The Dec. 10 meeting is open to the public at the North County Governmental Center. The board's recent agendas have included a public comment period.